Area Closures: DVT Southwest Apron Project

Dates


  • September 3 - September 10
  • Daily Closure: 6:00 AM to 6:00 AM (24-Hours)


  • Specific Closures


  • Ramp 1: Closed Sept. 5, 6:00 AM - Sept. 10, 6:00 AM
  • Access Road & Maintenance Bay: Closed Sept. 5, 6:00 AM - Sept. 6, 6:00 AM
  • Hangars 1-3: Closed Sept. 3, 6:00 AM - Sept. 4, 6:00 AM and Sept. 6, 6:00 AM - Sept. 7, 6:00 AM
  • Hangars 4 & 5: Closed Sept. 4, 6:00 AM - Sept. 5, 6:00 AM and Sept. 9, 6:00 AM - Sept. 10, 6:00 AM


  • General Information


  • All areas will close daily at 6:00 AM and reopen the next morning at 6:00 AM.
  • Tenants should contact Airport Operations for access details.
  • Please be cautious of personnel, barricades, and equipment.
  • Increased vehicle activity in the area is expected.
  • The contractor will inform Operations and the DCS Inspector before and after construction activities.


  • Activities


  • Hangars 1-3: Crack Seal (Sept. 3), Painting (Sept. 6)
  • Hangars 4 & 5: Crack Seal (Sept. 4), Painting (Sept. 9)
  • Access Road & Maintenance Bay: Crack Seal (Sept. 5), Painting (Sept. 6)
  • Access Road & Maintenance Yard: Pavement Maintenance


  • Contractor


    City of Phoenix Airfield Maintenance