East Economy Lot Pavement Rehabilitation
Scope: Work includes paving, seal coat application, crack sealing, and striping
within the surface lot. The lot will be divided into seven phases to alleviate impacts
to parking operations. Work duration for each phase will be between 7-12 days
and parking restrictions within the areas will be implemented.
Status: Phase 1 is anticipated to begin early December 2012.
Contractor: Banicki Construction