Mesa Airlines Hanger Fire Suppression System
Scope: This project will consist
of installing two 45,000 Gallon water tanks
as well as a pump house.
This equipment will facilitate the newly installed
and upgraded
fire suppression system inside of the hanger.
Status:
Construction preparation is currently underway, work is
scheduled to officially begin Monday, February 15.
This project has an anticipated end date of Monday, June 6.
Contractor:
Caliente